LB_FLO
Mechanical
- Jan 17, 2024
- 4
Hello experts,
I am looking for your thoughts on the amount of times a weld can be repaired. From reading through ASME B31.3 I cannot see any guidance on a specific number. From searching online and through forums the usual answer seems to be initial weld plus 2 repairs is good practice.
We have a job that has had multiple repairs including some that have been repaired twice. Our customer has questioned this but to me we have followed the code and can refer to ASME B31.3 para 341.3.4 (f)
If any of the defective items are repaired or replaced, re-examined, and a defect is again detected in the repaired or replaced item, continued progressive sampling in accordance with (a), (c), and (e) is not required based on the defects found in the repair. The defective item(s) shall be repaired or replaced and re-examined until acceptance as specified in para. 341.3.3. Spot or random examination (whichever is applicable) is then performed on the remaining unexamined joints.
We have carried out 100% x-ray on all welds which was agreed with the customer at the beggining of the job.
The pipe is 1.5"NB SCH40 304/L.
Thanks for your thoughts.
I am looking for your thoughts on the amount of times a weld can be repaired. From reading through ASME B31.3 I cannot see any guidance on a specific number. From searching online and through forums the usual answer seems to be initial weld plus 2 repairs is good practice.
We have a job that has had multiple repairs including some that have been repaired twice. Our customer has questioned this but to me we have followed the code and can refer to ASME B31.3 para 341.3.4 (f)
If any of the defective items are repaired or replaced, re-examined, and a defect is again detected in the repaired or replaced item, continued progressive sampling in accordance with (a), (c), and (e) is not required based on the defects found in the repair. The defective item(s) shall be repaired or replaced and re-examined until acceptance as specified in para. 341.3.3. Spot or random examination (whichever is applicable) is then performed on the remaining unexamined joints.
We have carried out 100% x-ray on all welds which was agreed with the customer at the beggining of the job.
The pipe is 1.5"NB SCH40 304/L.
Thanks for your thoughts.