liby
Industrial
- May 18, 2001
- 5
Hi
We are producing a CR vessel, 2m diameter, 4m long, cylinder 8mm, heads 10mm. No manhole, so the second head had to be welded from one side only. We used a backing strip & 100% radiography. There were a few rejects which were repaired. Second test showed three rejects, two porosity & a tranversal 2cm crack. The manufactor says that welds with backing strip should not be filmed.
My first question: Does anyone know of a spec or work order which specify that a backing strip weld should not be tested ?
Second question: What is the accuracy difference, or which is better. Radiography or Magnetic particle test.
Thank you
Liby
We are producing a CR vessel, 2m diameter, 4m long, cylinder 8mm, heads 10mm. No manhole, so the second head had to be welded from one side only. We used a backing strip & 100% radiography. There were a few rejects which were repaired. Second test showed three rejects, two porosity & a tranversal 2cm crack. The manufactor says that welds with backing strip should not be filmed.
My first question: Does anyone know of a spec or work order which specify that a backing strip weld should not be tested ?
Second question: What is the accuracy difference, or which is better. Radiography or Magnetic particle test.
Thank you
Liby