In the terminal I work we have a couple of tanks in need to be reconstructed, new bottom and in some we need to also substitute the first ring.
These tanks are operating more than 40 years, I'm worried about the weldability of the new plates with the old one.
Anyone can indicate a test or a lecture were I can get more information about?
These tanks are operating more than 40 years, I'm worried about the weldability of the new plates with the old one.