i have got Silo which will be made from steel plates rolled and welded toghter this silo will operate as follows:-
it's Silo for pressure hot air from the bottom and liquid soap from sprinklers on the sides and the liquid burned to get dry powder soap & the vapor go from the top to another step of manufacturing.
So what weldings inspections should i made for the wedling between steel Plates.
Thanks in Advance
i have got Silo which will be made from steel plates rolled and welded toghter this silo will operate as follows:-
it's Silo for pressure hot air from the bottom and liquid soap from sprinklers on the sides and the liquid burned to get dry powder soap & the vapor go from the top to another step of manufacturing.
So what weldings inspections should i made for the wedling between steel Plates.
Thanks in Advance