KevinNZ
Mechanical
- Jun 12, 2003
- 832
Hi
We have to add a nozzle to an existing vessel. The vessel is carbon steel(SA-516 Gr 70) with 3mm 316SS cladding. The nozzle we are adding is 316 pipe. We have not worked on a cladded vessel before so would like some direction please. Weld details below. To make it more complex we have also comply with NACE MR0175. Vessel design is ASME VIII (Div=?)
1. What is the weld thickness for heat treatment requirements?
2. What PWHT is required?
3. Is a WPS for 316SS welded to carbon steel OK for this detail with the cladding?
Thanks
We have to add a nozzle to an existing vessel. The vessel is carbon steel(SA-516 Gr 70) with 3mm 316SS cladding. The nozzle we are adding is 316 pipe. We have not worked on a cladded vessel before so would like some direction please. Weld details below. To make it more complex we have also comply with NACE MR0175. Vessel design is ASME VIII (Div=?)
1. What is the weld thickness for heat treatment requirements?
2. What PWHT is required?
3. Is a WPS for 316SS welded to carbon steel OK for this detail with the cladding?
Thanks