EastEng1012
Structural
- Aug 16, 2017
- 17
Project Background: The project is rehabilitation of a concrete spillway at a dam. The spillway apron is being partially removed(removal of 2-3" of shotcrete surface) and removal of a minimum of 1/4" to sound concrete into the existing 18" concrete slab. This is being done via hydro demolition. A 6" concrete overlay will then be placed over the apron with a grid of reinforcement and drilled anchors into existing slab.
Question: As a precaution, I want to verify of the strength of the existing slab and calculate the maximum concrete removal before the existing slab will not be able to support the loading from wet concrete during placement of the overlay. The overlay will be placed in 12'x18' segment. The spillway apron is sloped at maximum 34deg from vertical. My question is for calculating the pressure of the wet concrete on the existing slab - should I use the ACI equations for calculating the lateral pressure based on the head and rate of placement? The loads seem very high and wanted to make sure I was calculating it correctly.
The designer's calculations show they only assumed the load to be concrete density*6" depth even though it is sloped. Is this correct?
Question: As a precaution, I want to verify of the strength of the existing slab and calculate the maximum concrete removal before the existing slab will not be able to support the loading from wet concrete during placement of the overlay. The overlay will be placed in 12'x18' segment. The spillway apron is sloped at maximum 34deg from vertical. My question is for calculating the pressure of the wet concrete on the existing slab - should I use the ACI equations for calculating the lateral pressure based on the head and rate of placement? The loads seem very high and wanted to make sure I was calculating it correctly.
The designer's calculations show they only assumed the load to be concrete density*6" depth even though it is sloped. Is this correct?