RFreund
Structural
- Aug 14, 2010
- 1,885
I received a question from a contractor asking to wet cure a slab on grade. However, they wanted to use Visqueen in lieu of burlap. They propose to soak the slab and cover it in visqueen for 5 days. There are no cure and seal products being used for this slab.
I had a few questions:
1. Does this seem like a possible option? My first questions is how/when would they "soak" the slab.
2. When/how are control joints made when you wet cure a slab?
3. Any reference material you could point me towards? Normally I would expect burlap to be wetted for about 7-14 days but the control joints need to be placed within a day.
Thanks!
EIT
I had a few questions:
1. Does this seem like a possible option? My first questions is how/when would they "soak" the slab.
2. When/how are control joints made when you wet cure a slab?
3. Any reference material you could point me towards? Normally I would expect burlap to be wetted for about 7-14 days but the control joints need to be placed within a day.
Thanks!
EIT