allthegearnoidea
Civil/Environmental
- Oct 30, 2019
- 1
Hi there everyone,
I got some test results for some quarry material from a supplier for a road material.
Say for example, if I need to put down the quarried material at 102% Standard compaction effort for a 100m x 10m road at 150mm thick... what's the density I'm actually looking at in the test report? What would the working out be besides volume of the road...
100 x 10 x 0.15 x density??
Right now I'm looking at a report that says the Standard MDD for the material is 1.99, at 9.8% OMC... would that mean I'd be going for the Bulk Density? I.e. 1.99 * (1 + .098) = 2.19 t/m3?
I've always used a "rule of thumb" for base courses and sub base materials through out my career... but would like to be slightly more refined...
Thanks!
I got some test results for some quarry material from a supplier for a road material.
Say for example, if I need to put down the quarried material at 102% Standard compaction effort for a 100m x 10m road at 150mm thick... what's the density I'm actually looking at in the test report? What would the working out be besides volume of the road...
100 x 10 x 0.15 x density??
Right now I'm looking at a report that says the Standard MDD for the material is 1.99, at 9.8% OMC... would that mean I'd be going for the Bulk Density? I.e. 1.99 * (1 + .098) = 2.19 t/m3?
I've always used a "rule of thumb" for base courses and sub base materials through out my career... but would like to be slightly more refined...
Thanks!