- Nov 19, 2007
- 4
During startup following a major outage (turbine, boiler controls), final steam temps to turbine inlet reached 1160 degrees(Rated 1000).This peak lasted less than 20 minutes. Over the course of 4 days of startup/tuning similar spikes were encountered but max temps reached were below 1160. What effects to turbine performance, if any, could be realized due to these conditions. Since the outage we have suffered a load reduction of 20 MWs (Rated 470) that has been attributed to "loss of turbine efficiency".