Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

What is code weld and when it's needed ? 1

Status
Not open for further replies.

Mous1747

Mechanical
Apr 11, 2013
91
What is code weld and when it's needed ?
 
Replies continue below

Recommended for you

Whenever a code is specified. For example, when its a coded vessel ie., a vessel that is designed and built to code and must be code stamped (certified) - Such as one made to ASME I, VIII etc, \If the design requires welding in construction (or repair), then within those codes you would get directed to the welding code ASME IX.

Elaborate on your question for a meaningful answer...

*** Per ISO-4126, the generic term 'Safety Valve' is used regardless of application or design ***

*** 'Pressure-relief Valve' is the equivalent ASME/API term ***
 
There are pressure vessel codes, piping codes, structural welding codes, etc. Generally, the codes will specify how weld procedures are tested and qualified, how welders are certified, etc.
Generally, needed when the finished work is to comply with one of those codes.
 
A "code weld" is a weld complying with a specific welding code.

It's needed to comply with a specific code which includes welding.

This could be pipe construction, pressure vessels, structural design or other where welding is used to join things together.

If you cube us a bit more you might get more in return....

Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
 
Thank you guys for all the valuable info and sorry my question wasn't very clear.

We are cutting a flange and replacing it with another flange. this flange being replaced is not on the pressure vessel itself but bolted onto one of the nozzles. does that make it a code weld/repair?

I guess i meant by my question is what is the boundary of the PV that will determine if the weld code or not code?
 
Well if you were placing a Pressure Relief Valve on such a flange on a coded vessel (say ASME VIII), the PRV would also need to meet code requirements. So I guess the answer is yes, the weld needs to follow code.

But you've still not stated what code you are working to...

*** Per ISO-4126, the generic term 'Safety Valve' is used regardless of application or design ***



*** 'Pressure-relief Valve' is the equivalent ASME/API term ***
 
"Code Welder' is how boilermakers describe themselves to indicate that what they do is superior to and more difficult than other kinds of welding.

"Everyone is entitled to their own opinions, but they are not entitled to their own facts."
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor