When replacing a short section of coded (B31.1) pipe which is to be shop fabricated, how much weld detail should be put on the shop drawings? Is it sufficient to state to which standard it is to be fabricated by or does each weld need to be detailed out as in an ASME Pressure Vessel drawing? Also should any calculations be performed if the section is being replaced with no changes.
Thanks!
CAP
When replacing a short section of coded (B31.1) pipe which is to be shop fabricated, how much weld detail should be put on the shop drawings? Is it sufficient to state to which standard it is to be fabricated by or does each weld need to be detailed out as in an ASME Pressure Vessel drawing? Also should any calculations be performed if the section is being replaced with no changes.