5
What safety & failure issues do I have to be concerned about on welding on the subject matter above.
If welding is not the route can lock ring flanges be used in this service.
 
Replies continue below

Recommended for you

Are you referring to a hot tap process or off-line, fully vented pipe system?
 
I don't see any weldability or safety issues. Make sure the weld preps have been cleaned and subject to NDT examination (surface) before welding.
 
I have noticed in the past that there are possibilities of subsurface discontinuties opening up under welding process. So I think that a UT thickness check of about 6" around the welded area be checked prior to welding.
 