IJR
Structural
- Dec 23, 2000
- 774
Friends
I have a slab on grade carrying storage loads. Somewhere this slab is interrupted by a wall that goes down into earth to form a part of a channel.
Now at the junction between the slab and the wall there is a 90 deg bend and a fill there is not likely to be well compacted being next to a wall which will be cast in place before the slab is cast.
What additional measures must be made down there
Thanks IJR
I have a slab on grade carrying storage loads. Somewhere this slab is interrupted by a wall that goes down into earth to form a part of a channel.
Now at the junction between the slab and the wall there is a 90 deg bend and a fill there is not likely to be well compacted being next to a wall which will be cast in place before the slab is cast.
What additional measures must be made down there
Thanks IJR