The weld depicted by the sketch is a T-joint with a single bevel groove. The weld may or may not be a complete joint penetration groove weld depending on several characteristics and what the engineer wants.
AWS D1.1 Structural Welding Code/Steel imposes several conditions on the design. If the weld is made without backing and the WPS is not qualified by testing without steel backing, the weld is considered to be a partial joint penetration groove weld. The allowable stress on the weld is severely limited due the expectation there is a crack initiator in the unfused root, much like a fillet weld.
The groove angle is required to fall within a specific range if the detail is prequalified per figures 3.3 or 3.4 (PJP or CJP respectively).
If the groove detail is prequalified the root opening must fall within a specified range and steel backing must be used if it is welded from one side and it is necessary to be a complete joint penetration groove weld. Again, figures 3.3 or 3.4 are applicable if the groove detail is prequalified per AWS D1.1.
If the weld does not meet all the metrics of a prequalified joint, the contractor is required to qualify the WPS by testing. It would be prudent to qualify the WPS using the groove detail expected in production.
AWS A2.4 is the specification for welding symbols. In general, the welding symbol should include the depth of the bevel, the groove angle, the root opening, and if the weld is a partial joint penetration groove weld; the required weld size.
If the drawing is being generated by the Engineer, i.e., it is a structural drawing, it is only necessary to include the notation CJP in the tail of the welding symbol or both the required weld size and the notation PJP in the tail of the welding symbol if working to AWS D1.1. It would be th fabricator's responsibility to add any additional information to the welding symbol needed by the welder.
Best regards - Al