Sep 26, 2006 #1 7431 Petroleum Feb 2, 2006 24 0 0 AU Hi, I don't understand why list so many calendar: global, project, and resource. What the purpose of these terms ?
Hi, I don't understand why list so many calendar: global, project, and resource. What the purpose of these terms ?
Sep 27, 2006 #2 Akhibi Mechanical Sep 19, 2003 48 0 0 GB The Global calendar contains calendars that can be used by all projects are available for all resources and activities Project calendar Contains a separate calendar dedicated for each project and available for the current project only Greg Akhibi Clearwaters Consulting Ltd Upvote 0 Downvote
The Global calendar contains calendars that can be used by all projects are available for all resources and activities Project calendar Contains a separate calendar dedicated for each project and available for the current project only Greg Akhibi Clearwaters Consulting Ltd
Sep 27, 2006 Thread starter #3 7431 Petroleum Feb 2, 2006 24 0 0 AU Thank you, Akhibi! Sometimes I am confused by so many different calendars. BTW, after the schedule finished in a project management team, the next step is print the plan and send to different engineers to review, or just submit to manager? Upvote 0 Downvote
Thank you, Akhibi! Sometimes I am confused by so many different calendars. BTW, after the schedule finished in a project management team, the next step is print the plan and send to different engineers to review, or just submit to manager?