Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

WHEN DO I PUT A PAD UNDER A MACHINE 1

Status
Not open for further replies.

bumpjones

Mechanical
Nov 9, 2000
44
0
0
US
Hello,
We are rearranging our manufacturing are and need to move several CNC machines and lathes. Where can I find quidance on when to pour a pad for a machine and when do not need a pad.

Thanks,
Bumpjones
 
Replies continue below

Recommended for you

at the shop i work at we moved a bunch of machines last year and this is what we did.

Poured new 12" thick floor for all the lathes, mills, and threaders.

Poured a 3' deep pad for our grinders and used expansion board to keep it seperate from the 12" floor.

I don't know what the standard is but our floors were only 3" to 5" thick in some spots thats why we did what we did, and most grinders need a good pad and its better to separate it from others. Hope this helps some
 
Modern machine shop had an article about a company that uses steel plate to set machines on. It improved accuracy and the didn’t have to relevel when the machine was moved. This was for smaller VMC’s.
Most machine manuals have foundation requirements in their installation section. Depending on the type of work, surrounding vibrations, and the type of machines you may have to adjust thickness and style.
 
Status
Not open for further replies.
Back
Top