BrentP
Materials
- Apr 12, 2013
- 8
Have a question as the title says, I have a vessel where the nozzle is a machined 1.5" XXH pipe. The pipe is tapered at the end from .265" to 0.063", where a flange is added and another pipe bolted to it.
So, my question is, which portion is the code dependant portion, the 0.265" which is 2.7" long and the shell to weld thickness, or the 0.0625 section which is the end and extends only 0.5" but has the flange welded to it?
If it matters, calculated required thickness s around 0.035"
Thanks
So, my question is, which portion is the code dependant portion, the 0.265" which is 2.7" long and the shell to weld thickness, or the 0.0625 section which is the end and extends only 0.5" but has the flange welded to it?
If it matters, calculated required thickness s around 0.035"
Thanks