The utility provided the three phase fault with X/R and the 1-ph fault with X0/R0. How do I map these values in the ETAP model? Which value should be compared to ETAP reports?
Is that the 3-Phase Fault 0.5cyc kA Symm. rms?
I mean it should not be the Asymm. kA or the 4cyc or the minimum fault, correct?
Is that the 3-Phase Fault 0.5cyc kA Symm. rms?
I mean it should not be the Asymm. kA or the 4cyc or the minimum fault, correct?