shaneelliss
Structural
- Oct 15, 2007
- 109
I am involved in a project that has a concrete contractor and a steel erector as two separate contracts. Neither contract specifies who is to provide leveling nuts or shims. In my mind the answer is obvious that the steel erector is to provide the leveling nuts or shims because they have a choice on how to set the level and don't have to use one over the other (shims or nuts). The concrete contractor provided the anchor rods and one nut, which is what the drawings require. The drawings also show 1.5" grout space between concrete and baseplate. The steel erector is saying that they can't install the columns until the concrete contractor provides him with leveling nuts. I tried looking in the code of standard practice, but don't see anything there. Is there a standard that says the erector is to provide these? Or is it the concrete contractor's responsibility? Or is it the responsibility of the owner to make sure that the contract specifies one way or the other?