S06
Mechanical
- Jun 15, 2019
- 9
The standards mentions that the pipes pressure tested should be no longer than 500m.
However, I have installed pvc sewer mainforce line more than 800 meter without conducting pressure test.
I just wanted to know, technical what will happen if we conduct pressure test for pipe length exceeding 500m.
However, I have installed pvc sewer mainforce line more than 800 meter without conducting pressure test.
I just wanted to know, technical what will happen if we conduct pressure test for pipe length exceeding 500m.