Here is a question that follows from Flbob’s question regarding shop-drawing approvals.
Why do we really have shop drawings submitted in the first place?
This is not a naive question. I have been in the construction field for 26 years. I know that shop drawings are required for the fabrication shop to be able to concentrate on their work without all the design details of other work and to allow them to control the production in the most cost advantageous way for them, but why review the drawings and then take no responsibility for the drawings.
We insist that the contractor submit shop drawings before beginning fabrication, hold up the start of fabrication until they are reviewed and returned, then if there is a problem we attempt to put the onus on the contractor.
This does not seem fair to me. If we are going to hold the work up so that we can review the drawings then we should assume some of the risk. If the risk is only the contractors than why hold him up in the first place.
I have a problem with the ethics of getting paid for reviewing the drawings and then not taking responsibility for the results of the review.
Here is my proposal. We make submittal of shop drawings optional for the contractor. Submittal of drawings is only a way to help the contractor check for any errors before the work starts. If the contractor produces a final product that is outside of the contract then the responsibility would clearly be his and his alone.
Rick Kitson MBA P.Eng
Construction Project Management
From conception to completion
Why do we really have shop drawings submitted in the first place?
This is not a naive question. I have been in the construction field for 26 years. I know that shop drawings are required for the fabrication shop to be able to concentrate on their work without all the design details of other work and to allow them to control the production in the most cost advantageous way for them, but why review the drawings and then take no responsibility for the drawings.
We insist that the contractor submit shop drawings before beginning fabrication, hold up the start of fabrication until they are reviewed and returned, then if there is a problem we attempt to put the onus on the contractor.
This does not seem fair to me. If we are going to hold the work up so that we can review the drawings then we should assume some of the risk. If the risk is only the contractors than why hold him up in the first place.
I have a problem with the ethics of getting paid for reviewing the drawings and then not taking responsibility for the results of the review.
Here is my proposal. We make submittal of shop drawings optional for the contractor. Submittal of drawings is only a way to help the contractor check for any errors before the work starts. If the contractor produces a final product that is outside of the contract then the responsibility would clearly be his and his alone.