Mike Mike
Structural
- Apr 27, 2019
- 136
A situation that arises on many projects: contractor forgot U bars at column tops or installed them at the wrong elevation, poured columns, and then asks me for a correction. My intent is to transfer some moment between slab and column, and I frequently find my column tensile steel is like 5 or 10 times what's needed. A class B lap on a typical column vertical requires a drill and epoxy solution with a drill bit several feet long, and it appears ACI ties my hands by forcing me to develop the full yield strength of the bar: "Reduction of development length in accordance with 25.4.10.1 is not permitted in calculating lap splice lengths." (ACI318-14 25.5.1.4)
ACI408R-03 says "The extra length required [by ACI318] for Class B splices is not based on strength criteria but rather is used as an incentive for designers to stagger splice locations."
Darwin, Lutz, and Zuo say "Although tests demonstrate that splice strength where (As required) / (As provided) < 1 is conservatively represented by the modification factor in [section] 2.5, this factor is not used to increase the level of reliability of lap splices."
I understand the committees want to incentivize me to detail my splices to be staggered in new construction. But in my situation, if I calculate a one foot embedment satisfies the remainder of code provisions and presumably provides a reliability index of at least 3 or 4 (failure probability of one in several thousand), why do we need to punish the iron workers with having to drill several feet into column tops? Shouldn't the committees be striving to achieve uniform reliability across design? Let me know if I'm missing something here.
ACI408R-03 says "The extra length required [by ACI318] for Class B splices is not based on strength criteria but rather is used as an incentive for designers to stagger splice locations."
Darwin, Lutz, and Zuo say "Although tests demonstrate that splice strength where (As required) / (As provided) < 1 is conservatively represented by the modification factor in [section] 2.5, this factor is not used to increase the level of reliability of lap splices."
I understand the committees want to incentivize me to detail my splices to be staggered in new construction. But in my situation, if I calculate a one foot embedment satisfies the remainder of code provisions and presumably provides a reliability index of at least 3 or 4 (failure probability of one in several thousand), why do we need to punish the iron workers with having to drill several feet into column tops? Shouldn't the committees be striving to achieve uniform reliability across design? Let me know if I'm missing something here.