curiousinvite
Civil/Environmental
- Apr 24, 2021
- 42
I was trying to test reinforced wire mesh on point load . I modelled the rebar as wire element and assigned it as beam section . I applied tie constraint on horizontal and vertical rebars. The load is only transferred to the applied wire and it is not transferred to adjacent wire. what is the problem?