Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

AASHO-IV Girder - Bridge Crane Runway 5

Status
Not open for further replies.

SteveGregory

Structural
Jul 18, 2006
554
I am trying to analyze a prestressed girder dated about 1960. The company wants to upgrade the bridge crane from 50 tons to 85 tons.

Does anyone have any information on the prestress used then? How about load tables? I have a copy of a 1971 PCI handbook. The concrete tests showed about 5000 psi.
 
Replies continue below

Recommended for you

An old AASHTO spec probably wouldn't give you any information on the particular girder you are looking at as girders come in all shapes, sizes, levels of reinforcement, levels of prestressing, etc.

Without the original design documents pertaining to that girder, you will have to verify its strength in some other way such as a load test.

 
Another option to consider: - Design the (assumed) new 85 ton crane such that it imparts the same loads onto the runway system as the exisitng 50 ton. ie; more end truck wheels spaced farther apart, restirct hoist approach to runway beams (assists with veritcal load only). We have successfully put a 30 ton crane on a runway designed for 10 tons by doing this. Additionally. You will find that a new 85 ton hoist will weight the same or less than and "older" 50 ton. Hoist wieght contributes to lateral load into runawy beam.
 
Now that's good lateral thinking by FLCraneBuilder. Just goes to show, when you need a good answer, ask the right person.
 
I have done some bridge ratings and often found it possible to get behind the ends of the beams and count the strands and determind the strand pattern.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor