The steel sub fabricated the thru plates wrong and ended up with a 3/4" distance from the edge of the HSS column to the edge of the beam flanges. These are moment connections using thru plates on the HSS col. As a result, they will be unable to CJP weld this 3/4" distance. Is there a code req somewhere, or any reference, that tells us how much weld length is needed for CJP? I guess if it's a PJP or fillet weld we can find the strength and length to see if it'll transfer the loads, but CJP assumes that it will fully transfer all the loads (but what length is required? and what happens if that full length is not available)?