Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Rail beam LTB support / FBD help

Status
Not open for further replies.

RattlinBog

Structural
May 27, 2022
175
I have an interesting rail beam support / free body diagram situation that I'm struggling to wrap my head around. A little embarrassed to admit, but I could use some guidance. See attachment.

Location is an existing railcar unloading pocket for crushed rock. Rail is supported by W24x145 beams, which are continuous over several box girders. On either side of the open dump pocket are 4" slabs supported on W6x12 beams spaced 6 ft on center.

The W6 beams attach to the W24 top flange with a unique connection that has a slotted keyway parallel with the W24 beam and rail. I believe these slots allow for thermal expansion. There's also a double 2-1/2x2x1/4 angle that connects to a web stiffener on the W24 and to the bottom flange of the W6. I believe these are primarily for bracing the bottom flange of the W24 to prevent LTB in negative bending.

Without going into too much detail, the time has come to rebuild the 4" slab, W6 beam, and brace floor system. We're looking at a complete replacement of the slab, floor beams, and braces. The W24s, rail, and box girders will stay as-is.

In my attachment, I started a concept for a new slab/floor beam/brace design. I don't love it, but I'm trying to improve the original design from the 1970s. I have concerns about applying torque on the W24 with a 10" eccentricity at the beam seat. Perhaps the L3x3x1/4 brace will counteract the torque, but I'm not confident in that. Please take a look at my FBDs and critique...I don't think they're quite right. I haven't worked with a system like this before. If it is right, I'm seeing that the original/existing design dumps a lot of axial load into the W24 from the offset brace connection. I'm trying to mitigate that with the new design.

In summary, what would be a good way to brace the W24 for LTB while avoiding large torque or dumping axial forces into it inadvertently? Thanks in advance


 
 https://files.engineering.com/getfile.aspx?folder=22de2928-aa7a-41b0-8c2c-0e5218f2aca6&file=Rail_beam_existing_vs._new_concept.pdf
Replies continue below

Recommended for you

Sorry for the bump. Wanted to make a final attempt to see if anyone has some comments or suggestions. I'll leave it alone if there are no replies--no big deal.

I checked my FBD with my grad school professor (I'm working full time and a part-time grad student), and he thought I was on the right track. He agreed that I would have to consider torsion at the W24.

Curious if others have suggestions on how to make a better detail at the W24 connection. I've considered a deeper beam (W10 or W12 instead of W8), cope the top flange, and attach to W24 with clips or single plate. However, I have concerns with constructability and block shear rupture with such a large cope. Without going into too many details, let's just say there's a reason we are replacing the entire floor system. It's punished on a daily basis by abuse and misuse. I want to make the new floor bulletproof.
 
Sure, let's work through this.

1) I like the original detailing. Better than yours frankly. What is it that you don't like about it?

2) I would expect the triangulated frame that is the W6, the W24, and the 2L's to act as roll bracing to provide torsional LTB restraint to the W24. This is just as you explained it earlier.

3) Under this model (#2), the framing transverse to the W24 does not induce girder torsion but, rather, restrains it. This model should also put the double angles in tension rather than compression.

 
c01_x6mzrn.png
 
Thanks KootK. That makes more sense. I think I messed up by pinning the top and bottom flange of the W24. When I pin the bottom flange, it restrains the 2L brace and puts it in compression from the distributed load. When the bottom flange is allowed to rotate, then I can see how the 2L is in tension to resist that rotation.

I don't necessarily dislike the original connection detail to the W24, but I don't think it'll work as nicely with a 6" slab. My top of concrete needs to stay the same, so I'll lose 2" of stiffener depth if I were try to use the original connection. I was also concerned about the 2L brace dumping a bunch of axial load into the W24 due to the offset connection at the W6, but that seems to be a nonissue.
 
My beef with your detail is that it doesn't grab the top flange convincingly. You want that for torsional restraint. Maybe run the seat stiffener all the way up and slot the horizontal plate around it.
 
Agreed on the detail--it's not my favorite. I'll extend the stiffener like you suggested at a minimum. I'll sleep on it some more and see if I can think of anything better.

I found this thread on compression flange restraint that I'll read through, too: Link[URL unfurl="true"]https://www.eng-tips.com/viewthread.cfm?qid=306870[/url]

Attached are my latest calcs on the beam/brace LTB frame. The results seem reasonable.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor