hey ;
after transformer oil degassing operation , should i measure the winding resistance insulation ? if yes what the standar
 
Replies continue below

Recommended for you

It's not necessary. If you opened any current path or operated a tap-changer to wipe the contacts, then only winding resistance measurements need to be repeated.
 