bridgebuster
Active member
- Jun 27, 1999
- 3,966
In my office, we're trying to understand why the AASHTO group loading for box culverts is substantially different than the group loading for a rigid frame. It relates to a project we're involved with. We're extending an existing two-span box structure, which was constructed as a cut and cover tunnel. Our work involves placing a roof slab across the approach structure [bathtub or boat section]. The center pier will also be extended. The bathtub is "U" shaped; the retaining walls supported on a common footing.The span lengths are 28' and the clearance above the lower roadway is 15'. There's no significant fill above the structure. If we use AASHTO Group X for culverts, the existing walls are OK; if we follow the group loadings for concrete rigid frames, the walls fail; primarily due to temperature.
Back to the AASHTO criteria: For example, the beta factor for earth pressure for a culvert is 1.0; for a concrete frame it is 1.3. Also, temperature forces are neglected in culvert design but not for a frame.
Regarding the earth pressure differences, one of the geotech's thought it had to do with compaction of backfill, i.e, a culvert would be constructed in a narrow trench unlike a bridge. Therefore the forces from the compaction operation against the structure would be less. However, I've seen culverts constructed in large cuts with the slopes laid back to avoid sheeting. The compaction operation was no different than that for a bridge.
On the temperature issue, I would tend to agree with neglecting temperature effects on a culvert if there was significant fill above it. However, I've looked at some DOT manuals and old calculations; temperature is neglected even when there is no fill.
Any thoughts?
Back to the AASHTO criteria: For example, the beta factor for earth pressure for a culvert is 1.0; for a concrete frame it is 1.3. Also, temperature forces are neglected in culvert design but not for a frame.
Regarding the earth pressure differences, one of the geotech's thought it had to do with compaction of backfill, i.e, a culvert would be constructed in a narrow trench unlike a bridge. Therefore the forces from the compaction operation against the structure would be less. However, I've seen culverts constructed in large cuts with the slopes laid back to avoid sheeting. The compaction operation was no different than that for a bridge.
On the temperature issue, I would tend to agree with neglecting temperature effects on a culvert if there was significant fill above it. However, I've looked at some DOT manuals and old calculations; temperature is neglected even when there is no fill.
Any thoughts?