Recent content by Cherri

  1. Cherri

    Work hours

    I know, and I'v tried this. But when Project is calculating man-hours it still uses 7,5h, even if the workhoures in the calendar is from 07:30 - 19:30 (w/ breaks in between). Therefore I guess it uses the "hours per day" in Tools -> Alternatives -> Calendar to calculate workhours. But is this...
  2. Cherri

    Work hours

    I'm managing a project with two groups of workers. The first group is working 37,5h a week. The second group is working 62,5h a week. I can't seem to find a way to solve this without using the units-field. (E.g. A standard week = 62,5h. 0,6 units equals 1 man) That way is not an option for...