  1. kedpe

    Can replace 57 with 4 and not compact?

    Thanks DRC1: The excavation is very wet, and he mentioned that is one of the reasons he wanted to do it. If there are no fines in 3/4" stone, where is the fine migration coming from? The earth adjacent to the trench? Why doesn't clean stone need to be compacted to a proctor?
  2. kedpe

    Can replace 57 with 4 and not compact?

    Item 304 consists of: Sieve % passing 2 in (50mm) 100 1 in (25mm) 70-100 3/4 in (19 mm) 50-90 No. 4 (4.75 mm) 30-60 No. 40 7-30 No. 200 0-13
  3. kedpe

    Can replace 57 with 4 and not compact?

    The contractor has clarified his request was to use a # 4 stone in lieu of the 304 limestone called out for backfill in paved areas. He says that although # 4 stone is more costly than the 304 but they are of the opinion that with # 4 stone you don't run the risk of settlement issues which...
  4. kedpe

    Can replace 57 with 4 and not compact?

    I have a contractor asking if he can place a sanitary sewer, backfill w/ 57 stone to a foot over the pipe, then backfill the rest with 4-saying he wouldn't need to compact this. It is in a future parking lot (1-2 years out). Does anyone have experience in this area?
  5. kedpe

    HEC-RAS Ver 4 - has anybody tried it?

    I am using this version and (re)learning the software. I have 4 XS with Q=1330 cfs through a bridge. It has created the BU and BD and I am getting a warning that says: For the final momentum answer at the bridge, the upstream energy was computed lower than the downstream energy. This is not...
  6. kedpe

    Contraction joint-mesh and dowel placement

    I have a contraction joint detail with 18" dowel bar (in basket) centered about a T/4 deep sawed joint. The welded wire fabric is shown ending 12" from each side of the joint. This produces a 3" gap with no reinforcing, since the dowel bar is only 9" on either side of the joint. Should the...
  7. kedpe

    Utility Trench repair

    Thank you, bridgebuster. Also, thanks to DTGT2002.
  8. kedpe

    Utility Trench repair

    Are the drawings you refer to available online? The website doesn't appear to link to any digital files.
  9. kedpe

    Utility Trench repair

    Thanks for the info, bridgebuster. What is NYCDOT? New York City DOT?
  10. kedpe

    Utility Trench repair

    Large automaker plant expansion--continual semi traffic. Owner wants concrete repair whether ashpalt or concrete surrounding. Dowel only if connecting to concrete.
  11. kedpe

    Utility Trench repair

    One of my clients has asked for a detail that shows trench repair with concrete reinforced with #10 mesh with 6"x6" openings tied into the existing concrete by dowels. Any thoughts or sources on this?
  12. kedpe

    Is there a PIV that is flush with the ground?

    Thanks, guys. I did find one that is flush. But it wasn't FM approved. So, I rerouted a little, so that I could group 3 together. Then put bollards around the group.
  13. kedpe

    sanitary sewer services-

    Thanks, guys-yes, the existing lateral penetrated an existing mainline manhole. A new penetration was proposed because it was originally installed incorrectly (trying to make "it" flow uphill). So, a new inside drop was proposed ~2' lower in the manhole. The standard drawing for a service...
  14. kedpe

    Is there a PIV that is flush with the ground?

    I've rerouted an existing fire loop around a new building on a manufacturing plant site. The owner wants a PIV at every valve location. These are surrounded by 4 bollards. The 2 valves I need to make the connection to existing fire main are in very awkward locations to have an above ground...
  15. kedpe

    Measuring TIFF file

    Do you mean to measure various parts on a drawing with a scale? Usually I insert the record drawings that have been scanned to TIFF into Autocadd, then scale it up to 1:1 using the identified drawing scale. It is not very accurate and depends on the resolution of the TIFF.
  16. kedpe

    sanitary sewer services-

    Just for the laterals, not mainlines.
  17. kedpe

    sanitary sewer services-

    Why are manhole connections not allowed (discouraged) for sanitary sewer services? A standard drawing for a lateral connection shows a "trench dam" at 10' from the connection. What does a trench dam do, and is it used when the connection is to a manhole?
  18. kedpe

    Pond outlet culvert-HW & anti-seep collar question

    I want to use a 12" pipe to outlet a detention pond. It is only 30' length going thru the embankment. The profile will slope up 4:1 to provide 2' of cover over 10' of the pipe, then slope back down 4:1. I planned on using a HW at the inlet and outlet end. When is anti-seep collar needed?
  19. kedpe

    Site work in a Michigan winter

    I just got a project near Coldwater,MI with an aggressive schedule. What aspects of site work can be done in a Michigan winter? I'm in central Ohio.
  20. kedpe

    civil site design - project management advice?

    I had the same opportunity about 10 years ago and had about 5 years experience, to start a civil arm of an environmental firm. No other engineers, except my competitors. In hindsight, I would have taken a position with a firm that had more experienced engineers to mentor me. Best of luck...