Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  • Users: dflva
  • Order by date
  1. dflva

    Concrete Masonry Bearing Walls 12" to 8" transition

    Who on the project team wants to do this? How does placing the joists directly opposite one another on either side of the wall help the project? Chances are this doesn't work out over very much of the floor area anyway because of openings in the slab. Are the joists exposed to view? Is this...
  2. dflva

    Wind load on a Retaining wall

    Yes, consider anything doweled into the top of the wall an extension of the stem.
  3. dflva

    Wind load on a Retaining wall

    It sounds like you have a 3m tall CMU sail over the stem of the conc retaining wall. I would dowel the CMU into the top of the wall and apply wind loads. If you want to use the intermittent (concrete??) columns, perhaps the CMU can be supported on three sides using bond beams within the CMU...
  4. dflva

    contractor not following plans... at all

    It sounds like the Owner placed your drawings on the shelf and sometime between 2021 and now commissioned a new design. How do you know that they are building from your design at all?
  5. dflva

    Macombie steel joists

    Perhaps the manufacturer is Macomber? Search the site - there are a number of posts.
  6. dflva

    Foundation/Helical Pile Contractors

    If this exercise is for pricing, I think the Contractor and the Engineer could work for the buyer. If the objective is to perform construction at the property, the Contractor can't work for the buyer - he doesn't own the property!
  7. dflva

    PEMB continuous footing to resist sliding

    I have designed foundations for a handful of PEMB projects. I have not considered the continuous footings adjacent to the spread footing in resisting sliding, but I agree there is some legitimate amount of contribution. Determining a reasonable limit on the effective length of footing is a...
  8. dflva

    Technical drawing reviewing too time consuming?

    OP: Agree, checking shop drawings can be somewhat boring, but it is very important as clearly explained above. In going from school to work you may have been caught off guard by the shop drawing review portion of the job. Not every aspect of working in an office is previewed by a course at...
  9. dflva

    Pipe attachment to brick veneer

    I like NorthCivil's idea of connecting to the shelf angle.
  10. dflva

    RETAINING WALL FOUNDATION AT DIFFERENT LEVELS

    The change in elevation shown in Option 1 is too large for a single step. Step the foundation down using two or three steps along the length of the wall.
  11. dflva

    16" vs 8" bond beams

    I'm sure you're right about the architect being mad. I suspect this is due to eliminating the joint at 8 in. above opening.
  12. dflva

    Existing glass block above window - need fast lintel ideas

    In your second photo, there is a thin horizontal white band between the glass blocks and the top of the window frame. What is that? Perhaps it is a steel plate with hangers placed between the glass blocks?
  13. dflva

    Raised concrete pads under mechanical equipment

    Use a concrete pad for equipment anchorage. Anchors can be set in fresh concrete of pad using a template. Tie the concrete pad to the slab with reinforcing steel. Akin to using a conc pedestal between a footing and a steel column base plate. Also to accommodate long anchor rods a concrete...
  14. dflva

    Spreadsheets Vs Software

    I would prefer the software product. However for transparency I prefer Mathcad worksheets that I write myself. I've also done a handful of decent C (not C++) programs for more complex problems. I've never understood why someone who is capable of writing wiz-bang Visual Basic code (btw I'm not)...
  15. dflva

    Basement Retaining Wall - Sliding

    I agree with XR250. I provide one layer of building paper (30 lb roofing felt) on vertical surface (face of wall, etc) as a bond breaker. I have seen a slab stick to the wall (over about a 3 ft length) and cause a shrinkage crack (also 3 ft long) parallel to the wall about 1 ft out from the...
  16. dflva

    Stair Nosing Bar - Conflict w/ Recessed Step Light

    Eliminate the 3/4" x 1" dirt collector at the bottom of the riser and lower the light box. You need more concrete over the light.
  17. dflva

    PT design by others

    I designed a number of post-tensioned buildings in the early 2000s. Design process for all of them was exactly as KootK described above. Post-tensioning is alive and well in the Mid-Atlantic US.
  18. dflva

    Steel columns sitting on thermal blocks at braced bays

    The mention of bushings made me think of something: perhaps the lug can be wrapped in thermal break material, 4 sides + bottom? Just throwing it out there
  19. dflva

    Metal Building Foudnation Design

    Many of us have received this over-design rant from an owner or contractor at one time or another. I find they're usually leaving a piece of the design out in their comparisons. Examples: Owner: "My last building having the same spans used only a 7 in. slab, yours is way too thick at 8 in." ...

Part and Inventory Search