Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. EastEng1012

    Modal Analysis and Mesh Refinement

    Hello, We are running a modal analysis on a tank structure (modeled with shell elements. We have run several modal analyzes for the model with different mesh sizes to evaluate the mesh sensitivity. The modal analysis results appear to have similar cumulative mass participation but the...
  2. EastEng1012

    Headwall Design with Horizontal Span to WingWalls

    I am designing headwall with fairly large conduit opening (8-foot diamter). The headwall has wingwalls at 45-degrees. The headwall will need to extend about 3-4 feet above the conduit per the civil grading. I am designing the headwall above the conduit to span horizontally to the wing walls to...
  3. EastEng1012

    Valve Vault Top Slab w/ Multiple Access Hatch Openings

    Retired13 - yea sorry, those are floor plans, the hatches were highlighted in that plan view to show the key equipment the openings would cover. The roof plan has not been updated yet to include the new hatch openings. Thanks for suggested layout of beams. That was generally what i was thinking...
  4. EastEng1012

    Valve Vault Top Slab w/ Multiple Access Hatch Openings

    Sorry I thought I attached the sketch in my original post (see attachment)https://files.engineering.com/getfile.aspx?folder=4df8b80b-3177-4a7d-a9b4-0e406e41d0bf&file=Document1.pdf
  5. EastEng1012

    Valve Vault Top Slab w/ Multiple Access Hatch Openings

    Did you use a steel deck or just the wide flange supporting the underside of the slab?
  6. EastEng1012

    Valve Vault Top Slab w/ Multiple Access Hatch Openings

    Hey All, I am designing a cast-in-place rectangular valve vault structure. Owner requested CIP instead of precast. There are several structures with different dimensions (5'x10', 5' x 15', 10' x 20'). They are 6-feet deep. They will have a non-traffic live load (300 psf). We originally designed...
  7. EastEng1012

    Wing Wall/Retaining Wall Analysis (varying retained backfill height)

    Thank you all for your responses! It seems the consensus is to use the worst case condition which would be the starting height section and carry the design throughout the length of the wall. I agree that this is the best way to keep it simple both from a design standpoint and constructability...
  8. EastEng1012

    Wing Wall/Retaining Wall Analysis (varying retained backfill height)

    Hey All, I am curious on how others approach the design and/or analysis of wing walls (e.g., for culvert headwall) or any type of retaining wall with the height of the wall sloping downward to match the grading (varying retained back fill height). Generally what approach do you take: 1)...
  9. EastEng1012

    Existing Concrete Headwall Analysis (and Increasing Height)

    I struggling with exactly where the new footing would be located in your suggestion. Correct me if I am wrong, but the new footing would be located at the downstream end of the wing walls. So the kicker/strut run on top of the wing wall and where the existing wingwall terminates, there would be...
  10. EastEng1012

    Existing Concrete Headwall Analysis (and Increasing Height)

    Thanks dhengr for the response! I like the idea of constructing a horizontal beam to span across the top of the head wall for the added height and also above the wing wall for the load path. When you say slopes down to a new footing are you referring to extending the wing walls downstream in...
  11. EastEng1012

    Existing Concrete Headwall Analysis (and Increasing Height)

    Hey All, I am working on a project in the early phases that involves slope stabilization of an embankment. There is a head wall for a twin barrel (84-inch diameter) culverts on the downstream slope of the embankment. The re-grading to stabilize the slope requires increasing the height of the...
  12. EastEng1012

    Wet Concrete Pressure in Sloped Slab Overlay Application

    Hokie66 - that is correct that it is more of a wall then slab. The 34 degrees is at the steepest part of the spillway. The contractor is planning on using forms to place the new concrete.
  13. EastEng1012

    Wet Concrete Pressure in Sloped Slab Overlay Application

    The slab is not a slab on grade. It is an overflow section of the concrete dam which is essentially hollow on the inside. The slab is simply supported and spans between buttresses.
  14. EastEng1012

    Wet Concrete Pressure in Sloped Slab Overlay Application

    Correct, 18" concrete slab with 2" of shotcrete.... The shotcrete will be completely removed and a minimum of 1/4" into sound concrete. The issue will be if more concrete is removed than anticipated due to deterioration and the means and methods being used. The existing slab will then be loaded...
  15. EastEng1012

    Wet Concrete Pressure in Sloped Slab Overlay Application

    Project Background: The project is rehabilitation of a concrete spillway at a dam. The spillway apron is being partially removed(removal of 2-3" of shotcrete surface) and removal of a minimum of 1/4" to sound concrete into the existing 18" concrete slab. This is being done via hydro demolition...
  16. EastEng1012

    Built-Up Column - Double Channel Axial Load Capacity Approach

    I am evaluating an existing surge tank at a hydro-plant for code compliance. The surge tank consists of steel riser and cylindrical tank with 8 built up columns supporting the tank at the springline. The columns are braced with rods and struts at 3 locations. The built-up column consists of...

Part and Inventory Search