Hi!
What do you think about connection 2 different standards.
My Client wants to do pressure vessels acc. PED, manufacturing acc. EN 13445,
but at the same time calculating, designing and delivery of material acc. ASME.
I'm just trying to figure out how to do it.. and I still don't know.
Any...
Thanks XL83NL,
I reading and reading this standard and in my opinion,
NDT tests I must also do for welds for supports.
But I'm still wondering
is the number of these tests for supports the same for as for pipelines?
Hello Guys,
Who knows how to understand the EN 13480-5 standard for non-destructive testing?
is this standard saying that research should also be used on supports? that is,
the support should also be examined, for example, PT or MT.
Please find attachment.Who will...
Hello Guys,
Can somebody explain me one issue
namely, do I need to always applied the reinforcing plate
when I weld the legs to the bottom head (acc. sketch attachment)
Thanks!!!!https://files.engineering.com/getfile.aspx?folder=4e8dddc9-a137-41c4-abfc-c6b1f0a75d0d&file=Reinforcing_plate.jpg
Hello everyone,
Does anyone know where should I install the self-closing gate in exactly this case shown in the picture in attachment?https://files.engineering.com/getfile.aspx?folder=2275db20-3212-4971-a3f8-f9802164eb40&file=safety_gate.jpg
Hello Guys,
what requirements must meet the vessel with 3A SS (sanitary standard)
Well, I have to say, this is a first for me and I don't know even that whether the
factory have to have any special permition and certifation?
Does the vessel must be marked any sign after fabrication?
Anyone know...
Kołnierz_kryzowy - sketch in attachmenthttps://files.engineering.com/getfile.aspx?folder=afd79dc6-c476-4856-92eb-c225c63276f0&file=Ko?nierz_kryzowy.pdf
extracted from UDT's guidelines below.
(UDT - one of the polish NoBo)https://files.engineering.com/getfile.aspx?folder=e02abfd4-9df8-4d74-883f-7bf399a14b21&file=UDT.jpg
Hey Guys,
when I have design temperature about 300 C grade for vessel pressure then
I have to use weld neck flanges for nozzles,
is that guideline applies to manhole as well? What you thing about this?
I've just made a call to my BoDy and he exactly say the same thing;
I mustn't: put in CE marked on Tee (fittings), write somewhere PED
and submit declaration of conformity.
(Exeption: We can CE marked, but always after positive acceptance
by NoBo, verify welds, welders, documentation ect.
but...
Hello,
maybe I specify more detail:
let's assume that I'm a tee maker. First I prepare drawing and submit to my Client in order to approve it.
After that I'm actually doing it (I buy the material first – for example P265GH acc. PED then I weld it, thread it
- it's made acc. to the client's...
Hello, everybody here,
can someone help me i'm stuck;
what requirements must meet a tee, which will be subject to the PED 2014/68/EU?
Medium: group I (hazardous); pressure: 1,5bar; temperature: 40C?
In declaration of conformity I have to include every single detail
as I do it during pressure...
Hello,
vapor pressure for this medium in designed temp. for vessel presure are lower than 0,5 bar in designed temp. (confirmed by supplier).
So base on NoBo will not make any changes.
However without comfirmed vapor pressure for this medium it's very likely that they would have still reguired...
XL83NL
Thank you! It's very helpful.
The thing is the medium come from China
and it is some difficulty, because in our market it is doesn't exist.
i have a meeting tomorrow with NoBo and we will talk
but I must prepare myself in order to don't make a misstake.
So again thank you.
Hello people,
Are there some kind of reason the NoBo wants to change my classification
acc. PED 2014/68/UE for vessel pressure (medium: liquid, danger (flameable); V=50000l; design pressure: 3bar).
My result was Module A, named like: Internal Production Control, I marked CE but without NoBo...