Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. RabitPete

    Sizing coped beam fillet and electrical continuity in steel structures

    Check out the cope quality @2:30-2:31 mark Link What are your thoughts about the beam on the left?
  2. RabitPete

    Sizing coped beam fillet and electrical continuity in steel structures

    Found this on YouTube and looks like all of the faying surfaces are cleaned to the bare metal Link In our case it was not called by the drawings and out of state erector chose to do it since that's what they always do. I just personally never seen it done before and was concerned with the...
  3. RabitPete

    Sizing coped beam fillet and electrical continuity in steel structures

    I am looking at 2015 version of D1.1 and its section 5.16, it does specify 3/8" for the weld access holes but nothing for copes other than "Beam copes and cut surfaces in connection materials shall be free of sharp reentrant corners." So 3/8in should probably be a safe minimum for copes on...
  4. RabitPete

    Sizing coped beam fillet and electrical continuity in steel structures

    It is a 3 story office/commercial building, there are no slip critical connections on the plans. Contractor said they always do it to ensure electrical contact for proper grounding. I've never seen it done before on similar structures and nobody does it on PEMBs either, yet framework is always...
  5. RabitPete

    Sizing coped beam fillet and electrical continuity in steel structures

    I could not find any code reference to the minimum fillet size when designing coped beams. Which version on the pic below do you guys like more? Those are normally laser or plasma cut from 2 directions, so they rarely match perfect and typically leave some stress concentrators anyway And sort...
  6. RabitPete

    Welding in k-area and 1/2" recommended clearance

    Thanks, I've seen that AISC report, and imagined they would have done more research on the topic since 1997. It specifically mentions highly restrained joints which shear tab is not. Coping the bottom flange of the beam will reduce the capacity, as flexural local buckling becomes a controlling...
  7. RabitPete

    Welding in k-area and 1/2" recommended clearance

    Most discussions I've seen regarding welding in k-area were about stiffener plates. Any issues with starting a shear tab weld right from the point of tangency between the fillet and a web? Also, part 9 recommends 1/2" clearance and I am a little short under the bottom side of the top girder...
  8. RabitPete

    CMU vs ICF R-Values, cost and efficiency

    @masonrygeek: You probably mean a plain unreinforced CMU, right? I am not familiar with FL practices and mostly deal with commercial projects. After adding rebar, grout and union mason labor, CMU is typically comes up more expensive than RCC. On larger jobs tilt up RCC, PEMB and traditional...
  9. RabitPete

    CMU vs ICF R-Values, cost and efficiency

    I've seen several DIY ICF projects, CMU on the other hand takes some skill to do right. Renting wall forms like those used for basements and pouring RCC walls might be faster and easier than CMU. Hiring a professional masonry contractor will cost you arm and leg, especially if you want it...
  10. RabitPete

    Existing CMU building reinforcement

    Regardless of reinforcement method, wall has to transmit lateral load to the foundation. In our case bottom cutout was a little larger to allow for a hammer drill, so holes could be drilled into the wall footing under the CMU. Deformed bars were installed into those holes using adhesive anchors...
  11. RabitPete

    Existing CMU building reinforcement

    We had a project a few years back where we had to add reinforcement to the CMU wall. 1970s construction, CMU wall had horizontal durawall mesh, but zero vertical reinforcement. We added fully grouted vertical rebar every 3ft: 3 or 4 CMU faces were cut out along each vertical line, mortar...
  12. RabitPete

    Raised concrete pads under mechanical equipment

    I was thinking that pouring thicker equipment pads first is easier and they can also be isolated this way, and subgrade can be on the same level. But keep debating if making the pad isolated and hence much smaller and lighter would do more bad than good. I really admire pad workmanship on the...
  13. RabitPete

    Column Anchoring

    If it is an existing column without known dimensions, column itself can be used as a template to drill holes in the plywood. Then use drilled plywood as a template to secure anchors and leave it in place until concrete is set. Most steel erectors we work with insist on pouring foundation...
  14. RabitPete

    Raised concrete pads under mechanical equipment

    Any benefits of isolating those house keeping pads from the rest of the slab with expansion joints? Would isolated pad result in less sound/vibration transferred through the slab to the office space nearby? This is a slab on grade situation.
  15. RabitPete

    Raised concrete pads under mechanical equipment

    I see mechanical equipment being installed on top of raised concrete pads all the time. What is the reason those pads are raised? Why not make them same level as the rest of the slab? The one on the 2nd picture appears to be isolated from the floor slab, while the 1st one seems to be not...
  16. RabitPete

    Baseplate (with axial & moment) on unreinforced slab on grade

    Curious if anyone is using isolation joints when cutting in a new patch of concrete? Any code reference to when isolation joints are required? I see them added around interior column pedestals sometimes, while in many other cases slabs are poured right against pedestals.
  17. RabitPete

    Adding a footing to the existing slab - dowels? vapor barrier?

    Dowels will probably not help much. In case of a differential settlement they will simply break out of the existing slab, inspected the worksite today and the slab is only 4" to 5" thick
  18. RabitPete

    Adding a footing to the existing slab - dowels? vapor barrier?

    When adding a thicker, reinforced footing in a middle of the existing PEMB slab, any pros and cons of tying new footing to the old slab with rebar dowels? There is a granular fill under existing slab, and it always makes me nervous, as excavation results in gaps under the old slab around the...
  19. RabitPete

    Utility trench backfill - gravel over sand

    To clarify things, the reason I specified sand + gravel is because trench is crossing concrete pavement. So the trench gets filled with sand first, and then entire area gets gravel/crushed rock before the slab is poured. Slab is subject to heavy vehicular traffic (loading dock area).
  20. RabitPete

    Utility trench backfill - gravel over sand

    Any issues with using gravel on top of sand while backfilling utility trenches containing PVC pipes? Would a geotex between sand/gravel be useful or is it overkill?

Part and Inventory Search