canwesteng
Structural
- May 12, 2014
- 1,700
Does anyone have any experience using concrete with a one day cure time? I'm aware of the use of high early strength concrete for three day cures, but one day seems a little quick in my experience. If we were to go one day strength of 35 MPa (say using high early strength concrete with a 70 MPa 3 day or whatever the plant decides on), are there issues with letting the concrete cure only one day? I would expect substantial cracking because the concrete must be releasing lots of heat