We have a 42" ; 2 piece side entry ball valve, 300# used for subsea application to be installed on PLEM.
The question is for 2piece side entry ball valve which has a welded body, the welding point is potential for leakage..so how can it be avoided..the body is forged..and does the welded part needs 100% radiography and seal welded..??
Does anyone has experience in this..
The question is for 2piece side entry ball valve which has a welded body, the welding point is potential for leakage..so how can it be avoided..the body is forged..and does the welded part needs 100% radiography and seal welded..??
Does anyone has experience in this..