Beams, girders, or slabs supported by columns or walls shall not be cast or erected until concrete in the vertical support members is no longer plastic.
I have a condition where a contractor wishes to pour two separate decks with an connecting column in the same sequence. I am looking for a ACI manual reference which defines plastic. This may or may not determine if they accomplish this.