StrEng007
Structural
- Aug 22, 2014
- 537
It's been stated here before that using #57 and #67 stone is a common approach to beams and slabs. I'm questioning whether or not those aggregates are actually too large?
Per Sieve analysis, #57 stone is comprised of a majority 3/4" stone and has up to 5% that is larger than 1" and less than 1-1/2". Put differently, #57 stone has a maximum aggregate size of 1-1/2" with a majority of the composition at 3/4".
Similarly #67 stone has a maximum aggregate size of 1" with a majority of the composition at 1/2".
Outside of exposure requirements, ACI has three sections that relate aggregate size to reinforcement/spacing.
STATEMENT #1
In section 25.2.1, it requires that non-prestressed bars in a single larger should maintain the greater or 1", db, or (4/3)dagg.
STATEMENT #2
However, section 25.2.2 says non-prestressed bars placed in two layers need to maintain a clear distance of 1" between bars.
STATEMENTS #3, #4, #5, as (i), (ii), (iii), RESPECTIVELY
Section 26.4.2.1.a.5 requires the aggregates not to exceed the following
5) Nominal maximum size of coarse aggregate not to exceed the least of (i), (ii), and (iii):
(i) one fifth the narrowest dimension between sides of forms
(ii) one-third the depth of slabs
(iii) three fourths the minimum specified clear spacing between individual reinforcing bars or wires, bundles of bars, prestressed reinforcement, individual tendons, bundled tendons, or ducts
[highlight #FCE94F]My questions are:[/highlight]
•Why does Statement #2 not address the 4/3dagg if the purpose of that is to make sure concrete flows properly? If a #57 stone is used in these situations, the max aggregate is larger than the clear spacing.
•Based on the information above, if you use 1" spacing between bars, then Statements #1 and #5 require that all aggregates be ≤ 3/4" (#57 & #67 doesn't satisfy either of these requirements).
•Does clear spacing also mean clear cover? As in, if you maintain 1-1/2" of clear cover to the form work... does that mean you have to limit aggregate size to 3/4xCC? 1-1/8 (or 1")
•For interior slabs with 3/4" clear cover to top/bottom reinforcing, would you not be required to use 0.75x3/4" = 1/2" max aggregates?
Per Sieve analysis, #57 stone is comprised of a majority 3/4" stone and has up to 5% that is larger than 1" and less than 1-1/2". Put differently, #57 stone has a maximum aggregate size of 1-1/2" with a majority of the composition at 3/4".
Similarly #67 stone has a maximum aggregate size of 1" with a majority of the composition at 1/2".
Outside of exposure requirements, ACI has three sections that relate aggregate size to reinforcement/spacing.
STATEMENT #1
In section 25.2.1, it requires that non-prestressed bars in a single larger should maintain the greater or 1", db, or (4/3)dagg.
STATEMENT #2
However, section 25.2.2 says non-prestressed bars placed in two layers need to maintain a clear distance of 1" between bars.
STATEMENTS #3, #4, #5, as (i), (ii), (iii), RESPECTIVELY
Section 26.4.2.1.a.5 requires the aggregates not to exceed the following
(i) one fifth the narrowest dimension between sides of forms
(ii) one-third the depth of slabs
(iii) three fourths the minimum specified clear spacing between individual reinforcing bars or wires, bundles of bars, prestressed reinforcement, individual tendons, bundled tendons, or ducts
[highlight #FCE94F]My questions are:[/highlight]
•Why does Statement #2 not address the 4/3dagg if the purpose of that is to make sure concrete flows properly? If a #57 stone is used in these situations, the max aggregate is larger than the clear spacing.
•Based on the information above, if you use 1" spacing between bars, then Statements #1 and #5 require that all aggregates be ≤ 3/4" (#57 & #67 doesn't satisfy either of these requirements).
•Does clear spacing also mean clear cover? As in, if you maintain 1-1/2" of clear cover to the form work... does that mean you have to limit aggregate size to 3/4xCC? 1-1/8 (or 1")
•For interior slabs with 3/4" clear cover to top/bottom reinforcing, would you not be required to use 0.75x3/4" = 1/2" max aggregates?