RARWOOD
Structural
- Jun 17, 2004
- 519
I attended a seminar last week presented by Lawrence A. Kloiber of LeJeune Steel Company Minneapolis, Mn on practical connections using the 2005 AISC. I work for a glulam fabricate and design glulam connections. However I could relate very well to his discussion on the use of actual loads.
He showed several examples of cases where the EOR used a standard table for specifying connection load requirements and where the EOR uped the load for CYA reasons. In his examples he should the connections designed for the loads on the drawings and what the connection would look like if designed for the actual load.
I haven't done any major steel design for almost 10 years so I could not relate his examples to any steel connections. However I could relate them to numerous cases where the drawings required the design of glulam connections for many times the actual load.
One example I thought of was where the engineer added 15 psf to the roof dead load just in case the jowner added a ballasted roof in the future. In another example the engineer required designing for a drift load which would have been 2' above the roof parapet causing the drift.
The problem with not specifying the actual loads for wood connections is that it goes against the general principle of using the smallest number of fastners in the wood to reduce potential problems in the connections.
As you increase the number of connectors you increase the stiffness of the joint and you also increase the potential for the connectors to cause splitting as the member dries in place.
So as a wood designer I strongly endorse Mr. Kloiber advice to specify the actual loads.
He showed several examples of cases where the EOR used a standard table for specifying connection load requirements and where the EOR uped the load for CYA reasons. In his examples he should the connections designed for the loads on the drawings and what the connection would look like if designed for the actual load.
I haven't done any major steel design for almost 10 years so I could not relate his examples to any steel connections. However I could relate them to numerous cases where the drawings required the design of glulam connections for many times the actual load.
One example I thought of was where the engineer added 15 psf to the roof dead load just in case the jowner added a ballasted roof in the future. In another example the engineer required designing for a drift load which would have been 2' above the roof parapet causing the drift.
The problem with not specifying the actual loads for wood connections is that it goes against the general principle of using the smallest number of fastners in the wood to reduce potential problems in the connections.
As you increase the number of connectors you increase the stiffness of the joint and you also increase the potential for the connectors to cause splitting as the member dries in place.
So as a wood designer I strongly endorse Mr. Kloiber advice to specify the actual loads.