FEM4Structures
Structural
- Jan 1, 2014
- 48
Trying to come with anchor Pull-Out Test Load embedded in concrete.
Say the service live load is 1 kip. (Assume all Live)
Is it correct to multiply 1 kip with (1.6/0.7) for a total Test Load of 2.43 kips. Such that FOS for LL= 1.6 and Phi =0.7 for concrete tension capacity equations per ACI 318 Appendix D.
Thanks,
FEM4Structures
Say the service live load is 1 kip. (Assume all Live)
Is it correct to multiply 1 kip with (1.6/0.7) for a total Test Load of 2.43 kips. Such that FOS for LL= 1.6 and Phi =0.7 for concrete tension capacity equations per ACI 318 Appendix D.
Thanks,
FEM4Structures