Inspecting a warehouse system I found where the installing contractor was using CPVC downstream the inspector's test valve, downstream the 2" main drain angle valve and on the 3/4" supply from the alarm check valve to water motor gong.
Seemed strange to me but I can't find anything wrong with it. Not the way I do things but is there something I am missing?
Seemed strange to me but I can't find anything wrong with it. Not the way I do things but is there something I am missing?