Is Code Case 19-15 in direct conflict with 341.3.1(a)?
Interpretation: 19-15
Subject: B31.3-1999 Edition (2001 Addenda), Para. 331.1.1, Heat Treatment Requirements and Para. 341.3.1, General
Date Issued: July 1, 2002
File: B31-02-03070
Question (2): In accordance with ASME B31.3-1999 Edition (2001 Addenda), para. 341.3.1, is NDE examination of piping constructed of P1 or P2 materials required to be performed after final heat treatment?
Reply (2): No.
vs
341.3.1(a) For P-Nos. 3, 4, and 5 materials, examination shall be performed after completion of any heat treatment.
Thank you in advance.
Interpretation: 19-15
Subject: B31.3-1999 Edition (2001 Addenda), Para. 331.1.1, Heat Treatment Requirements and Para. 341.3.1, General
Date Issued: July 1, 2002
File: B31-02-03070
Question (2): In accordance with ASME B31.3-1999 Edition (2001 Addenda), para. 341.3.1, is NDE examination of piping constructed of P1 or P2 materials required to be performed after final heat treatment?
Reply (2): No.
vs
341.3.1(a) For P-Nos. 3, 4, and 5 materials, examination shall be performed after completion of any heat treatment.
Thank you in advance.