Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

ASME Section VIII Div I: Repair - Rewelding of A Coupon Back onto A Pressure Vessel 1

Status
Not open for further replies.

craigjw

Chemical
Jan 22, 2015
2
I am seeking guidance for acceptable repair to a pressure vessel. In this instance, a fabrication shop punched a hole in the wrong spot of a pigging barrel (see attached picture). After notifying 3rd party inspection, they took the plug (same material grade, composition and thickness) beveled it back and shot 100% x-ray on the repair spot. Additionally they did a 14 hour hydro test at 1800 PSI on the vessel (1.5 x design).

I'm coming up short for answers when searching ASME Section III Div I. Is this an acceptable repair? If not, what, if anything, is considered acceptable?

Greatly appreciated.
 
 http://files.engineering.com/getfile.aspx?folder=5abeffb6-0c58-45c7-aad7-70aac39be2c2&file=image1.jpeg
Replies continue below

Recommended for you

I am not familiar with section III so I am not positive, but I don't think that will fly with the code or the client. The shell of the vessel is obviously out of round at the repair site. Is there a tolerance on vessel roundness? Is the fabricator a qualified R-stamp holder? I don't think anyone would let that slide as new fabrication. If I ordered a vessel, and that showed up on my door step I would not be a happy camper.
 
craigjw, this kind of thing happens fairly reqularly and the repair you describe is generally condsidered acceptable for Sec VIII, Div 1 work, assuming full penetration welding of course. Only relevant section I know of is UG-78.

Unfortunately the repair in your picture looks not good at all, as the owner I would not be happy.

Regards,

Mike
 
SPDL310: I apologize, I meant Section VIII. Thank you for the response. I have asked one of my inspectors who is a CWI to chime in. So far we are stacking hands on rejecting this fab job.

SnTMan: That was also the only relevant section I could find as well. I agree, it looks like poor workmanship.

Thank you both for your replies!
-Craig
 
There is nothing in Section VIII to prohibit this type of fabrication repair to correct a nonconformance. The surface should have been ground flush to ensure no local stress concentration.
 
This is a heavy wall vessel and that valley left will not affect performance if meets Code for the over grind. The suck in may be for lock of pre heat and xrays will not see that. hopefully the inside looks same or better. I wary more on the design, those large reinforcing pads will not allow correct expansion-contraction.I'm not the greatest designer I just see things.
 
This is a common method of repair to a misplaced nozzle cut out in a Section VIII, Div. 1 vessel. When possible it is preferable to use the same cut out material to make the repair. You don't indicate whether this vessel was subject to PWHT, was it?
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor