JoeSeag
Mechanical
- Jan 24, 2024
- 12
I've seen rumors floating around for a few years that this section is being potentially revised/removed in future editions. Anyone have insight? In any case, I've followed this discussion for years and still haven't had much success resolving the intent, what to do with the "may" statement, and how to best implement it in the ever increasingly tight project schedules. We provide external nozzle load allowable charts to the PV vendor early on for their design of the shell/nozzle junction. However, as many have stated prior, using these same values for UG-44b would significantly increase flange ratings by many steps. Waiting for the piping stress analysis to be performed would result in many changes in PV design without disrupting schedules. What are folks doing these days? Uprating their flanges considerably? Delaying schedules with flange changes after pipe stress? Or something I've not thought of perhaps? Much appreciation for input!