Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Backfilling saturated soil

Status
Not open for further replies.

SiPaul

Civil/Environmental
Jul 25, 2003
64
We have an open excavation (50' x 25') that needs to be backfilled. It has filled up with rain water so the soil is generally saturated. We can pump out most of the water but is there a concern for for the satuarated soil? Eventually there will be a structure in the area but we don't anticipate being ready for foundations for another year. The area would be re-excavated at the time.
The excavation is 6-9' deep.

 
Replies continue below

Recommended for you

Well, what kind of soil is it? Do you know how much is saturated - 6 inches or 5 feet?
 
Generally sandy with some fill material. I am using the term saturated but it is really just wet at the surface (as far as I can tell). It seems that after a few days of dry weather it dries almost completely.
 
Well, if you can get it to dry, I would do that, and rework the top foot by scarifying, moisture conditioning and recompacting at project specs. I am not sure that you need to "excavate" 1 foot as SRE indicates, but it is definately more conservative (as in: not a bad idea). At a minimum, once it has dryed and is stable on the surface, cut in a ramp, and get some trucks in to do a proofroll.

The main thing is to get it stable and keep it dry. Having a slight slope to the subgrade / backfill, down to a pump is a good way to maintain this.

The contractor should protect his work. Obviously, this can be difficult with a big hole; therefore, there is no reason that you should not be able to ask the contractor to show the work completed / subgrade is suitable for placement of more fill.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor