Hello,
I am trying to determine why bolts are losing clamp load on a steel car port structure. My best guess is that a semi-constant low speed wind is causing cyclical loading in the bolts and structure. My problem now is that I need to run the calculations to determine if this is actually happening. Does anyone know of a standard or document that has calculations for how many load cycles a bolted joint can to go through before losing clamp load (how many cycles for a given external load)? Any help is greatly appreciated.
I am trying to determine why bolts are losing clamp load on a steel car port structure. My best guess is that a semi-constant low speed wind is causing cyclical loading in the bolts and structure. My problem now is that I need to run the calculations to determine if this is actually happening. Does anyone know of a standard or document that has calculations for how many load cycles a bolted joint can to go through before losing clamp load (how many cycles for a given external load)? Any help is greatly appreciated.