I have two earthgrids A and B. A is a power station with an 11kV 30MW generator and a 11/22kV step-up trfr. There is a 22kV cable from the trfr to a swbd on grid B 40metres away. Grid B is fed either from the power station or utility via a 132/22kV transformer situated on Grid B. Earthgrid B has been designed for a 132kV fault from the utility.
1) What fault level should Grid A be designed to?
2) Should grids A and B be joined or left seperate.
Thanks in advance.
1) What fault level should Grid A be designed to?
2) Should grids A and B be joined or left seperate.
Thanks in advance.