Andrew88
Civil/Environmental
- Aug 7, 2017
- 42
Hi all,
Let's assume I have a borehole pump 50m below ground. The dynamic water table during drawdown is 30m beloow the ground. Now I need to lift the pump assembly together with pipework that is filled up with water. The pump is equipped with NRV valve. For the initial lifting:
- can I subtract from the total calculated weight (pipework + fluid + pump + lifting assembly) the buoyancy force across 20m submerged depth?
- if yes to above, would I only consider volume of the pipe itself so really just a shaft as I imagine the pump would still allow flow into the tube so can't treat it as a whole cylinder?
As for the pad design, I need to make it pretty thick due to the punching shear. Would you put any reinforcement in a large cube of concrete, for the sake of discussion 2x2x1m deep. The coping would be at ground level.
Thanks a lot!
Let's assume I have a borehole pump 50m below ground. The dynamic water table during drawdown is 30m beloow the ground. Now I need to lift the pump assembly together with pipework that is filled up with water. The pump is equipped with NRV valve. For the initial lifting:
- can I subtract from the total calculated weight (pipework + fluid + pump + lifting assembly) the buoyancy force across 20m submerged depth?
- if yes to above, would I only consider volume of the pipe itself so really just a shaft as I imagine the pump would still allow flow into the tube so can't treat it as a whole cylinder?
As for the pad design, I need to make it pretty thick due to the punching shear. Would you put any reinforcement in a large cube of concrete, for the sake of discussion 2x2x1m deep. The coping would be at ground level.
Thanks a lot!