Dear All,
We have a 400V Switchgear fed from two 33/0.4kV transformers each on bus A and bus B. Then there is emergency incomer on bus E which is fed from 11kV emergency switchgear station via a 11/0.4kV transformer. Under normal operation emergency incomer breaker is open and bus tie BE is closed. Please refer to attached diagram for clear picture. When the supply from two normal transformer not available, bus tie BE will be opened and emergency incomer breaker will be closed(both are interlock to each other). The 400V switchgear now being supplied via 11/0.4kV transformer from 11kV emergency switchgear. At 11kV emergency switchgear there are two incomers as well. Normal supply is fed from 33/11kV transformer. When this supply is loss, EDG will start and supply the 11kV switchgear.
If the 400V switchgear being supplied by EDG only, during power restoration we can only do break before make i.e break 11/0.4kV incomer breaker and close bus tie BE? I was told by my senior this is due to the normal bus and emergency bus will not in synch since the downstream utility voltage has gone through completely different transformers. Please share if you have experienced a system configuration like this.
Appreciate your answers.
We have a 400V Switchgear fed from two 33/0.4kV transformers each on bus A and bus B. Then there is emergency incomer on bus E which is fed from 11kV emergency switchgear station via a 11/0.4kV transformer. Under normal operation emergency incomer breaker is open and bus tie BE is closed. Please refer to attached diagram for clear picture. When the supply from two normal transformer not available, bus tie BE will be opened and emergency incomer breaker will be closed(both are interlock to each other). The 400V switchgear now being supplied via 11/0.4kV transformer from 11kV emergency switchgear. At 11kV emergency switchgear there are two incomers as well. Normal supply is fed from 33/11kV transformer. When this supply is loss, EDG will start and supply the 11kV switchgear.
If the 400V switchgear being supplied by EDG only, during power restoration we can only do break before make i.e break 11/0.4kV incomer breaker and close bus tie BE? I was told by my senior this is due to the normal bus and emergency bus will not in synch since the downstream utility voltage has gone through completely different transformers. Please share if you have experienced a system configuration like this.
Appreciate your answers.