Cantilver slab to be poured later 4

Status
Not open for further replies.

canstructural

Structural
Sep 16, 2009
22
I have a situation ,where as per site requirements, cantilver slab of about 9ft will be poured later in the construction.

Please see the attached sketch and provide your opinion, is it possible to pour as one of the options. I am just wondering that there is no monolithic joint at the junction.

I can ask for bottom rebar to make continuous at support, if it requires to be.

Appreciate for your kind suggestions.
 
Replies continue below

Recommended for you

Would say:
- JAE's about cambering and rapt's about corrosion more than agree;
- 50% for me is comforable;
- do not hesitate to provide note about number of days this cantilevered part will be shored, in my opinion it's deflection controlled situation
 